Construction update

Construction is underway accross the project.

You can view the route and find out more about the infrastructure by clicking on our interactive map.

Project timeline

Scottish onshore works

 
timeline icon

2025-2026

Surveys and design work for Horizontal Directional Drilling (HDD).

timeline icon

2025 - 2028

Underground cable installation between Torness converter station and Thorntonlock Beach

timeline icon

2025 - 2028

Torness Converter Station construction and installation

timeline icon

2028

Completion of Torness Converter Station, and cable installation - system testing to begin

timeline icon

2029

EGL1 is energised

English onshore works

 
timeline icon

2025 - 2028

Murton Converter Station construction and installation

timeline icon

2026 - 2028

Underground cable installation between Murton Converter Station and Seaham Hall beach

timeline icon

2028

Completion of Murton Converter Station and cable installation - system testing to begin

timeline icon

2029

EGL1 is energised

Marine works

 
timeline icon

2027 - 2028

Installation of 176 km of subsea cables

timeline icon

2029

EGL1 is energised

Community Impacts  

To construct EGL1, we need to conduct a range of activities including surveys, building access roads, and out of hours work. On occasion, we will need to put in place traffic management measures, including road closures and traffic light systems, to ensure the safety of all road users and our workforce. 

During construction, you may notice: 

  • Increased construction traffic, including HGVs
  • Temporary traffic management such as road closures or traffic lights
  • Noise from activities such as piling and drilling
  • Visible construction works such as fencing and trenching

We understand this may cause disruption. 

We are working to keep impacts as low as possible and will keep communities informed throughout the works. 

Working hours 

Typical working hours are: 

  • Monday to Friday: 7:30am to 6pm
  • Saturday: 8am to 2pm

Occasionally, works may need to take place outside these hours. Where this happens, we will provide advance notice wherever possible. 

Community updates 

Details of our ongoing and upcoming traffic management measures can be found in the tables below. 

English construction updates 

Works  

Location  

Measures in place  

Expected timings  

Link to more information  

Steelworks 

Murton – Converter Station

N/A 

July 2026 – early 2027 

Autumn 2026 Newsletter 

Piling works 

Hawthorn Pit – Substation 
 
Murton – Converter Station 

Hydraulic hammer 

Non-metallic cushion and plywood packaging

February – August 2026 

Autumn 2026 Newsletter/ Resident Postcard 

Scottish construction updates 

Works  

Location 

Measures in place  

Expected timings  

Additional information 

Summer 24 hours Working 

Torness, Scotland 

Noise monitoring and silenced generators. Site will be illuminated at night. 

July 2026 – September 2026 

N/A 

Archived community updates 

Scotland 

Works  

Location  

Details of works  

Expected timings  

Additional information  

Horizontal direction drilling

Torness, Scotland 

N/A 

26 – 30 January 2026 

N/A 

Geotechnical surveys 

Shearwater barge – Torness Scotland

A jack up platform was installed to conduct borehole drilling, to provide information about the physical condition of the seabed.

28 July - 13 August 2025 

Marine Newsletter

England 

Works  

Location  

Details of works  

Expected timings  

Additional information  

Geotechnical surveys 

Sandpiper barge – Seaham Hall Beach 

A jack up platform was installed to conduct geotechnical surveys to provide information about the physical condition of the seabed.

10 - 28 July 2025 

Marine Newsletter

What we are constructing in your area 

Scottish works  

English works  

Marine works  

Torness area, East Lothian 

Work includes: 

  • Building a new converter station
  • Installing underground cables
  • Horizontal directional drilling
  • Temporary works such as access roads and compounds 

Seaham landfall to Hawthorn Pit, Murton, Durham 

Work includes: 

  • Building a new converter station and substation
  • Installing underground cables
  • Horizontal directional drilling
  • Temporary works such as access roads and compounds 

Marine works 

Work includes: 

  • Marine surveys
  • Seabed preparation
  • Installation of subsea cables